Progress on the Hoxton Hotel

Progress on the Hoxton Hotel

The five-storey rear extension is now fully constructed and installation of cladding and windows is well underway.  Internally we are working our way up from the bottom with the fit-out, partitions and first-fix M&E.  Screeding and ceilings are in progress throughout the floor plates.

We have completed the steel frame for the single storey extension to the roof of the existing Newton wing (with guests in rooms below) and the breakthrough from the new rear extension to the existing hotel wing has been formed at all levels.

The client is delighted with the progress and together with the on-site team we are negotiating a first-floor extension to the meeting rooms at GF level and re-modelling all of the ground floor public areas commencing on site on the 12/09/19.